YOUR
Search

    04.06.2022

    Incentives and difference between the authorized and declared power


    Italian Supreme Administrative Court - Judgment No. 1228/2022

     

    What happened

     

    The Italian Supreme Administrative Court has reformed the Lazio Regional Administrative Court’s ruling that upheld the measure by which the Gestore dei Servizi Energetici – G.S.E. S.p.A. (“GSE”) denied access to the incentives established by the July 6, 2012 Ministerial Decree for the construction of a new 200 kW wind power plant. The grounds for the denial regards the lack of possession of the connection quote at the time of registration in the Registry.

     

    In the case at stake, the applicant obtained (and accepted) from the grid operator a connection quote for a 900 kW power capacity. However, then the plant had been authorized and built for a capacity of only 200 kW.

     

    Subsequently, the operator applied for registration in the Registry, submitting the connection quote issued for 900 kW. While waiting for acceptance, it asked the grid operator for a downward modification (from 900 kW to 200 kW) of the connection quote.

     

    Nonetheless, the GSE and later the Lazio Regional Administrative Court held that the operator was not in possession of the connection quote at the time of registration in the Registry.

     

    The Italian Supreme Administrative Court argued for the acceptance of the operator’s appeal, underlining that the decrease in power is a permissible and non-substantial change under the January 2014 Application Procedures of the Ministerial Decree of January 6, 2012 (“Application Procedures”). Consequently, this difference, according to the Italian Supreme Administrative Court’s ruling, could not be considered an impediment to eligibility for incentives.

     

    Why is it matters

     

    It is clearly identified the function of the connection quote. The operator’s argument emphasizing its “reservation function is found to be acceptable. Accordingly, it is stressed that only the case where there is an increase in power is problematic.

     

    In fact, the Italian Supreme Administrative Court underlined that: “since the accepted connection quote has a function of “reservation” of the input power with respect to a grid point (so-called cabin), it is irrelevant in the authorization process that the plant originally assumed for a power (in the case of 0.9 MW) is eventually authorized for lower power (in the case of 0.2 MW), because by physical law a cabin that holds an input of higher power is able to hold a lower power; it would not be so for the reverse case of application for a lower plant and authorization for a plant of higher power”.

     

    Another highlighted aspect is that power decrease is not a substantial change” within the meaning of the Application Procedures. Consequently, if the power indicated in the connection estimate is greater than the power that has been realized and authorized this does not preclude the plant to be eligible for incentives.

    Energy Law Italy Outlook | November 2025
    The third issue of Energy Law Italy Outlook, the #newsletter published by ADVANT…
    Read more
    Fer Z: an innovative scheme to support renewables, system flexibility and market integration
    Italy’s upcoming Fer Z mechanism introduces a new approach based on programmable…
    Read more
    The Amendment to the Renewable Energy Law: outlook, contradictions and future scenarios
    One year after the approval by the Council of Ministers of Legislative Decree No…
    Read more
    Suitable areas: significant regulatory changes are underway. News and impacts on future investment strategies
    As is well known, for several months now the players in the energy and infrastru…
    Read more
    The new Energy Release 2.0 in light of the Comfort Letters, the Corrective Decree and the Operating Rules
    On 27 June 2025, the European Commission confirmed that the Energy Release 2.0 m…
    Read more
    Notification or publication in the Regional Official Bulletin: when does the time limit for appeal by the public administration begin?
    With its ruling no. 447 of 14 October 2025, the Abruzzo Regional Administrative …
    Read more
    Irrelevance of the material error and applicability of the tariff reduction
    Plants registered in the Registry: (i) irrelevance of material errors concerning…
    Read more
    Energy Law Italy Outlook | October 2025
    The second issue of Energy Law Italy Outlook, the #newsletter published by ADVAN…
    Read more
    The Lombardy Regional Administrative Court overturns the Regional Resolution on agrivoltaic plants: the introduction of restrictions not provided for by national legislation for the installation of agrivoltaic plants on agricultural land is unlawful
    With judgment no. 789 of 3 September 2025, the Lombardy Regional Administrative …
    Read more