YOUR
Search

    04.06.2022

    Incentives and difference between the authorized and declared power


    Italian Supreme Administrative Court - Judgment No. 1228/2022

     

    What happened

     

    The Italian Supreme Administrative Court has reformed the Lazio Regional Administrative Court’s ruling that upheld the measure by which the Gestore dei Servizi Energetici – G.S.E. S.p.A. (“GSE”) denied access to the incentives established by the July 6, 2012 Ministerial Decree for the construction of a new 200 kW wind power plant. The grounds for the denial regards the lack of possession of the connection quote at the time of registration in the Registry.

     

    In the case at stake, the applicant obtained (and accepted) from the grid operator a connection quote for a 900 kW power capacity. However, then the plant had been authorized and built for a capacity of only 200 kW.

     

    Subsequently, the operator applied for registration in the Registry, submitting the connection quote issued for 900 kW. While waiting for acceptance, it asked the grid operator for a downward modification (from 900 kW to 200 kW) of the connection quote.

     

    Nonetheless, the GSE and later the Lazio Regional Administrative Court held that the operator was not in possession of the connection quote at the time of registration in the Registry.

     

    The Italian Supreme Administrative Court argued for the acceptance of the operator’s appeal, underlining that the decrease in power is a permissible and non-substantial change under the January 2014 Application Procedures of the Ministerial Decree of January 6, 2012 (“Application Procedures”). Consequently, this difference, according to the Italian Supreme Administrative Court’s ruling, could not be considered an impediment to eligibility for incentives.

     

    Why is it matters

     

    It is clearly identified the function of the connection quote. The operator’s argument emphasizing its “reservation function is found to be acceptable. Accordingly, it is stressed that only the case where there is an increase in power is problematic.

     

    In fact, the Italian Supreme Administrative Court underlined that: “since the accepted connection quote has a function of “reservation” of the input power with respect to a grid point (so-called cabin), it is irrelevant in the authorization process that the plant originally assumed for a power (in the case of 0.9 MW) is eventually authorized for lower power (in the case of 0.2 MW), because by physical law a cabin that holds an input of higher power is able to hold a lower power; it would not be so for the reverse case of application for a lower plant and authorization for a plant of higher power”.

     

    Another highlighted aspect is that power decrease is not a substantial change” within the meaning of the Application Procedures. Consequently, if the power indicated in the connection estimate is greater than the power that has been realized and authorized this does not preclude the plant to be eligible for incentives.

    GSE as Guarantor in PPA Contracts: the Reform of the Emergency Decree
    IntroductionWith the approval of Decree Law No. 208 of December 31, 2024 (“Emerg…
    Read more
    The MASE publishes the Operating Rules of the FER 2 Decree
    Last 23 December, the Ministry of the Environment and Energy Security reported i…
    Read more
    The Sardinia Region approves the law for the identification of areas and surfaces suitable and unsuitable for the installation and promotion of RES plants
    On 5 December, the Regional Law no. 20 ‘Urgent measures for the identification o…
    Read more
    Greenfield: the latest case law
    The following is a review of the most relevant recent rulings on authorization p…
    Read more
    In-Depth Note: Unified Renewable Energy Code
    The Council of Ministers, during the meeting on 25 November 2024, approved the U…
    Read more
    Registration tax on deeds creating a right of superficies on agricultural land: application of 9% rate confirmed
    By Guido Martinelli e Sarah Eusepi. Roma, 8 Novembre 2024 1. Introduction The…
    Read more
    Discounted energy price will be offered to Energy Intensive Companies under the MASE Energy Release Decree
    On 23 July 2024, the Ministry of the Environment and Energy Security (“MASE”) ap…
    Read more
    The Sardinian Moratorium already before the Constitutional Court
    Regional Law no. 5 of 3 July 2024, with which the Council approved the so-called…
    Read more
    The Ministerial Decree on Green Conditionalities: clarifications and provisions
    The Ministerial Decree on Green Conditionalities provides the long-awaited clari…
    Read more