YOUR
Search

    04.06.2022

    Incentives and difference between the authorized and declared power


    Italian Supreme Administrative Court - Judgment No. 1228/2022

     

    What happened

     

    The Italian Supreme Administrative Court has reformed the Lazio Regional Administrative Court’s ruling that upheld the measure by which the Gestore dei Servizi Energetici – G.S.E. S.p.A. (“GSE”) denied access to the incentives established by the July 6, 2012 Ministerial Decree for the construction of a new 200 kW wind power plant. The grounds for the denial regards the lack of possession of the connection quote at the time of registration in the Registry.

     

    In the case at stake, the applicant obtained (and accepted) from the grid operator a connection quote for a 900 kW power capacity. However, then the plant had been authorized and built for a capacity of only 200 kW.

     

    Subsequently, the operator applied for registration in the Registry, submitting the connection quote issued for 900 kW. While waiting for acceptance, it asked the grid operator for a downward modification (from 900 kW to 200 kW) of the connection quote.

     

    Nonetheless, the GSE and later the Lazio Regional Administrative Court held that the operator was not in possession of the connection quote at the time of registration in the Registry.

     

    The Italian Supreme Administrative Court argued for the acceptance of the operator’s appeal, underlining that the decrease in power is a permissible and non-substantial change under the January 2014 Application Procedures of the Ministerial Decree of January 6, 2012 (“Application Procedures”). Consequently, this difference, according to the Italian Supreme Administrative Court’s ruling, could not be considered an impediment to eligibility for incentives.

     

    Why is it matters

     

    It is clearly identified the function of the connection quote. The operator’s argument emphasizing its “reservation function is found to be acceptable. Accordingly, it is stressed that only the case where there is an increase in power is problematic.

     

    In fact, the Italian Supreme Administrative Court underlined that: “since the accepted connection quote has a function of “reservation” of the input power with respect to a grid point (so-called cabin), it is irrelevant in the authorization process that the plant originally assumed for a power (in the case of 0.9 MW) is eventually authorized for lower power (in the case of 0.2 MW), because by physical law a cabin that holds an input of higher power is able to hold a lower power; it would not be so for the reverse case of application for a lower plant and authorization for a plant of higher power”.

     

    Another highlighted aspect is that power decrease is not a substantial change” within the meaning of the Application Procedures. Consequently, if the power indicated in the connection estimate is greater than the power that has been realized and authorized this does not preclude the plant to be eligible for incentives.

    Energy Law Italy Outlook | July 2026
    The new issue of Energy Law Italy Outlook is now available online. Prepared by…
    Read more
    Italy's carbon reimursement scheme faces trade-off between EU approval and market impact
    Italy’s proposed carbon costs reimbursement for gas-fired power producers may…
    Read more
    The final FER-X decree: the new quotas and the main changes compared to the transitional regime
    1. Premises  On June 18th, the Minister of the Environment and Energy…
    Read more
    “Decreto Bollette”: the role of GSE as guarantor of last call also for contracts entered into through the “Bacheca PPA”
    On 18 April 2026, Law No. 49/2026 was published in the Gazzetta Ufficiale,…
    Read more
    Important clarifications on the PAS by the Council of State
    With judgment No. 3325 of 28 April 2026, the Italian Council of State upheld the…
    Read more
    TRANSACTIONAL RISK INSURANCE IN ENERGY AND INFRASTRUCTURE M&A TRANSACTIONS
    Among the contractual risk-allocation tools typically used in M&A transactions,…
    Read more
    Investing in Data Centres: risks and opportunities following the conversion into law of the "DL Bollette"
    In order to catch up with international competitors, over the past year the…
    Read more
    Energy Law Italy Outlook | Vol.3-2026
    The new issue of Energy Law Italy Outlook, the newsletter edited by ADVANT…
    Read more
    On the electrification of port quays: the cold ironing system
    1. Introduction The electrification of port quays, known as “cold ironing”,…
    Read more