YOUR
Search

    03.06.2025

    The request for supplementary documentation by the public administration interrupts the forfeiture period for filing an appeal against administrative silence


    With judgments no. 324, 325, and 326 of May 26, 2025, the Regional Administrative Court (TAR) of Basilicata clarified that the deadline for filing an appeal against administrative silence is interrupted when the Public Administration requests supplementary documentation.

    In the proceedings concluded with judgments no. 324 and 325/2025, the situations were symmetrical. An application had been submitted for the issuance of the Single Regional Authorization Measure under Article 27-bis of Legislative Decree no. 152/2006 for the construction of a photovoltaic plant and related works to connect it to the national electricity grid. The Administration responded only three years later, requesting supplementary documentation. Although the applicant complied with the request, the Administration remained inactive, thereby failing to meet the 230-day deadline for concluding the procedure.

    In the case decided by judgment no. 326/2025, an application had been filed for the issuance of a Single Authorization for the construction and operation of a photovoltaic plant, to which the Region responded only two years later with a request for supplementary documentation. Here too, the Administration remained inactive, violating the 90-day deadline for concluding the procedure.

    Article 31, paragraph 2 of the Administrative Procedure Code (Codice del Processo Amministrativo – c.p.a.) states that an action against administrative silence “may be brought as long as the failure to act persists and, in any case, no later than one year from the deadline for concluding the procedure.”

    In all three cases, this forfeiture period had long expired, but the TAR of Basilicata nonetheless upheld all the appeals. This was because it considered that the Administration’s request for supplementary documentation constitutes an event that interrupts the time limit, whereas the request for suspension under Article 27-bis, paragraph 5, second sentence, of Legislative Decree no. 152/2006 — made by the private party and granted by the Administration — is irrelevant.

    Therefore, since the remaining procedural deadline for convening the Conference of Services began to run from the date on which the applicant responded to the request for supplementary documentation, the TAR, in all three judgments, ordered the Region of Basilicata to convene the Conference of Services and conclude the procedure.

    Conto Energia and the “Exit Strategy”: the Exit Decree has been published
    In implementation of the provisions of Article 2, paragraph 6, of Decree-Law No.…
    Read more
    Energy Law Italy Outlook | October 2026
    The new issue of Energy Law Italy Outlook is now available online. Prepared by…
    Read more
    Zero-impact ports: MIT sets the rules for cold ironing concessions
    1. Introduzione The electrification of port berths (“cold ironing”) is one of…
    Read more
    Definitive FER-X scheme: preliminary qualification as a new gateway to competitive procedures and its impact on the market
    Background With the MASE Decree of 18 June 2026 and the subsequent GSE…
    Read more
    VIRTUAL SATURATION OF THE GRID: THE NEW OPEN SEASON MODEL AND ITS IMPACT ON M&A TRANSACTIONS IN THE RENEWABLES SECTOR
    Background The total capacity of applications for connection to the RTN…
    Read more
    IN THE EVENT OF FORFEITURE, THE REPAYMENT OBLIGATION LIES WITH THE PERSON WHO ACTUALLY RECEIVED THE INCENTIVES
    In judgment No. 6267 of 3 August 2026, the Second Division of the Council of…
    Read more
    Energy Law Italy Outlook | July 2026
    The new issue of Energy Law Italy Outlook is now available online. Prepared by…
    Read more
    Italy's carbon reimursement scheme faces trade-off between EU approval and market impact
    Italy’s proposed carbon costs reimbursement for gas-fired power producers may…
    Read more
    The final FER-X decree: the new quotas and the main changes compared to the transitional regime
    1. Premises  On June 18th, the Minister of the Environment and Energy…
    Read more