    22.12.2025

    Important principles for the renewable energy sector from the Palermo regional administrative court


    With Decision No. 740 of 19 December 2025, the Sicilian Regional Administrative Court provided important clarifications for the renewable energy sector. 

    The ruling originates from an appeal against the refusal to grant an extension pursuant to Article 10-septies of Decree Law No. 21/2022 (also known as the “DL Ucraina”), based on (i) failure to meet the deadline for the start of works authorised in PAS and (ii) non-compliance of the project with the new urban plan adopted. 

    The Court clarified that: 

    • pursuant to Article 10 septies of Decree Law No. 21/2022, “the extension constitutes a mandatory act and does not require formal approval by the proceeding authority” (see TAR Campania, Salerno, Section II, 17 October 2025, No. 1701) upon the occurrence of the strictly prescribed conditions, including that the deadline to be extended has not expired and that “the authorisations are not in conflict, at the time of notification by the subject, with new urban planning instruments approved”; 

    • for works that can be authorised with a PAS (generally assimilated in case law to a SCIA), there is no deadline for the start of works under Article 6 of Legislative Decree 28/2011, while it is required that they be completed within three years of their finalisation; 

    • the mere “adoption” of an urban planning variation (not yet approved) that conflicts with the authorisation already issued is not sufficient to prevent the extension of the authorisation itself ex lege. 

    This is clearly a ruling of considerable importance, especially in light of the significant practical and economic implications for players in the sector, as it clarifies fundamental aspects – which until now have remained uncertain – that are destined to have a concrete impact on projects currently under development. 

    We are now waiting for the hearing, scheduled for 18 June. 

    Conto Energia and the “Exit Strategy”: the Exit Decree has been published
    In implementation of the provisions of Article 2, paragraph 6, of Decree-Law No.…
    Read more
    Energy Law Italy Outlook | October 2026
    The new issue of Energy Law Italy Outlook is now available online. Prepared by…
    Read more
    Zero-impact ports: MIT sets the rules for cold ironing concessions
    1. Introduzione The electrification of port berths (“cold ironing”) is one of…
    Read more
    Definitive FER-X scheme: preliminary qualification as a new gateway to competitive procedures and its impact on the market
    Background With the MASE Decree of 18 June 2026 and the subsequent GSE…
    Read more
    VIRTUAL SATURATION OF THE GRID: THE NEW OPEN SEASON MODEL AND ITS IMPACT ON M&A TRANSACTIONS IN THE RENEWABLES SECTOR
    Background The total capacity of applications for connection to the RTN…
    Read more
    IN THE EVENT OF FORFEITURE, THE REPAYMENT OBLIGATION LIES WITH THE PERSON WHO ACTUALLY RECEIVED THE INCENTIVES
    In judgment No. 6267 of 3 August 2026, the Second Division of the Council of…
    Read more
    Energy Law Italy Outlook | July 2026
    The new issue of Energy Law Italy Outlook is now available online. Prepared by…
    Read more
    Italy's carbon reimursement scheme faces trade-off between EU approval and market impact
    Italy’s proposed carbon costs reimbursement for gas-fired power producers may…
    Read more
    The final FER-X decree: the new quotas and the main changes compared to the transitional regime
    1. Premises  On June 18th, the Minister of the Environment and Energy…
    Read more